2001
Beneficial use of dredged sediment
United Kingdom
Hamford Water (Essex)
1.2526
51.8631
Habitat Enhancement
In 1998 and 1999, the marina's grab dredger was used to dredge the marina berths.
The sediment was placed into a barge before being broken down into a slurry and pumped into the recharge area.
A total of around 10,000 tonnes (approx. 8,000m³) per year were used in 1998 and 1999.
In 2001 there was further recharge to raise the bed level for saltmarsh plant development; a 60-80cm vertical overburden was placed in saltmarsh channels.
During 2002 and 2007 more material was recharged of fluid dredged material was placed on site. These were retained using Clay Bunds.